Why does the number differ from the old Excel report?

If you put OPEREX’s monthly availability next to your previous Excel report, the numbers can differ — and that is not a bug, but the consequence of a deliberate, more accurate counting rule. This page shows what the difference is, when the two agree, and how to compare them.

The difference comes down to a single question: which month owns an outage that spans the month boundary?

  • The familiar Excel report books the entire duration of the outage to the month in which it started (the report groups by start date).
  • OPEREX cuts the outage at the period boundary: each month gets exactly the part that actually falls into it.
JuneJulyReality: the outage starts on the evening of 30 June and lasts until 10 Julyoutage (10 days)Excel: ALL 10 days charged to June — July looks spotless10 daysOPEREX: June gets its own ~1.4 hours, the rest belongs to July~9.9 days

This is a DCPI plant’s June–July 2026 case (real data). The outage started on 30 June, ~1.4 hours before the end of the month, and lasted 10 days — until 10 July — for a total of 240 hours. June has 30 days = 720 hours, July has 31 days = 744 hours. Here is what each rule says about MONTHLY availability:

Month Old Excel rule
(start month gets it all)
OPEREX
(cut at the boundary)
June 66.7% — the full 240 hours land on June 99.8% — only June’s ~1.4 hours
July 100% — “spotless” 67.9% — the outage’s ~238.6 hours

Check it yourself: availability = (hours in the month − downtime hours) / hours in the month. Under Excel, June is (720 − 240) / 720 = 66.7% and July is (744 − 0) / 744 = 100%. Under OPEREX, June is (720 − 1.4) / 720 = 99.8% and July is (744 − 238.6) / 744 = 67.9%.

The Excel rule says June was the bad month and July was flawless — but it happened the other way round: the plant spent almost the entire outage in July. The OPEREX number tells the truth about both months: June was fine, July dropped. The same 240 hours — just booked where they belong.

Availability is a ratio: the share of the month’s hours during which the equipment ran. A ratio can only contain what actually falls into that month. Start-date accounting misleads in two ways:

  • It charges the wrong month. The example above is real data: a 10-day outage started an hour and a half before the end of the month. Under the Excel rule all 240 hours burden June — although only an hour and a half of it happened in June — while July looks spotless even though the plant stood still for 10 days.
  • It can produce impossible numbers. For a long outage spanning several months, the starting month gets more downtime hours than the month even has — “availability” then comes out as a negative percentage, which has no physical meaning. Meanwhile the months in between show 100% although the plant never ran.

The cut-based number always stays between 0% and 100%, and tells the truth about every month.

If no outage spans a month boundary, the two rules give the same number. The difference comes exclusively from boundary-spanning outages — the longer your outages, the larger it can get.

If you want to put the OPEREX number next to the old report:

  1. Open the month’s outages with the tile’s “Open source” link.
  2. Take the outages that started in this month — regardless of their end date.
  3. Add up their full durations: that is the Excel-style number. The OPEREX number counts, from the same outages, the part that falls into the month.