Creating and approving a risk assessment (step 0)

You assess the job first, and the assessment tells you which permit it needs and under which mandatory conditions. With the built-in settings one job gets one permit: its type is decided by the main hazard, and the supplementary hazards (lifting, electrical work, excavation…) are added as boxes of that permit. The process then does not start with picking a permit type (which easily happens out of habit) but with walking through the hazards of the job — and the assessment’s trail stays on every permit started from it.

You can make two kinds of assessment: an ad-hoc one for one specific job, and a pre-prepared one for a recurring type of work. The steps and pictures in this article show the ad-hoc assessment (“step 0”); for the pre-prepared one see the “Two kinds of assessment” table and the “Pre-prepared assessment” section.

  • Permission: creating and approving a risk assessment — ptw:assess. Creating the permit drafts from an ad-hoc assessment is a separate right: ptw:request or ptw:issue.
  • Prerequisite: you know on which site and in which plant the job will be done (for a pre-prepared assessment: which plant, site or the whole company it covers).
Ad-hoc Pre-prepared (recurring work)
What it covers One specific job. A recurring type of work.
How a permit comes from it After approval, Create permit drafts starts the permit, one for each type it prescribes. It is made and approved once; then it can be linked to any number of permits from the New permit drop-down while it is valid.
What is on the assessment The job’s data: time window, work order, requesting company, work supervisor, headcount. Only the type of work and the questions. The time window, work order, contractor, supervisor and headcount are entered on the permit.
Scope Plant. Plant, All plants on the site or Whole company (every site).
Expiry None. Yes; fixed at approval (it can also be no expiry).
Number KE-2026-V1BLOKK-00007 (with the site’s tag). The same; a company-wide one is KE-2026-CÉG-00001.
When the job changes Copy as draft. Review (new version).
Taking it out of use Void (not once a permit has started from it). Withdraw (also from the approved state).
The Step 1 — where and what the job is card: Site and Plant pickers, Job title, Place of work, Requesting company, Work supervisor and Description of the job fields, and the Create — the questions open next button at the bottom.
The first step of a new assessment: where and what the job is. The draft gets its number immediately.
  1. Open the Risk assessment tab and click “New risk assessment”. The form always has a Kind chooser at the top (the first option, Recurring job (pre-prepared), can only be chosen where the policy is on a drop-down option — elsewhere it is disabled, with a reason; where it can be chosen, it is selected by default); for this sequence choose the second option, One-off job (the steps for Recurring job (pre-prepared) are further down).

  2. Say where and what the job is. Choose the Site and the Plant, type the Job title, and if you know them, the place, the requesting company, the work supervisor and the Description of the job — what is done, with what, where. This is your own text: the questionnaire does not replace it. Click “Create — the questions open next”. The assessment gets a number starting with KE-.

  3. Complete the Basics. The Work order, the Planned start / Planned end and the Planned headcount are here too. Everything you type is saved automatically (All saved).

  4. Work through Hazard identification. They come in sections: the site-side and activity-side hazards are tick boxes, while material properties and circumstances (for example the Explosive atmosphere zone) are answered in their own sections, with a picker or a Yes · No · N/A switch. A question marked with a star is mandatory. The bar running along the bottom of the page always shows what is still missing (“… · unanswered required question”); click a missing item in the list and the page jumps to it.

  5. If your organisation asks for it, fill in the job safety analysis. In the Job safety analysis (JSA) table, per row: When (optional: before / during / after work, plus a free-text detail) · Activity · Hazard · Who can be harmed · S (severity, 1–5) · L (likelihood / frequency, 1–5) · R (risk) · Control measure · Owner · Reference. R = S × L is calculated by the system and coloured by its level (very low → very high); the scales and the level bands are behind the ⓘ of the column headers. The level bands come from the rule pack. Pointing at the R number (tapping it on a phone) opens a small 5 × 5 matrix with the row’s cell, the level name and what to do. Scoring is optional — a row without a score (and an earlier assessment) stays valid. Add row adds a row (it inherits the stage of the row above); on a desktop you see a two-band grid, on a phone one card per row. On an approved assessment and on the PDF, rows of the same stage are grouped together.

  6. If your organisation asks for it, fill in the PPE matrix. On the Mandatory PPE by body part card you state for each body part (Head · Hearing · Eyes / face · Respiratory · Arm / hand · Feet · Skin · Torso · Body (whole)) whether PPE is needed, and if so, its Type and EN standard. The card tells you whether filling it in is mandatory.

  7. Watch the live prescription. The What the assessment prescribes panel on the right (on a phone, a sheet that slides up with Open the prescription) shows, answer by answer, the Permit to issue: the type is decided by the main hazard (hot work · confined-space entry · Ex zone), and the supplements (lifting, electrical work, excavation…) are added as the permit’s questions. Below: the prescribed (🔒) and recommended (✧) items, the headcount and the conditions. The small info icon (i) next to each item, opened, tells you which rule prescribes it. When several types could issue the job, the Permit type chooser offers the recommended one (the narrowest covering every main hazard); if the policy says “the assessment’s permit proposal cannot be overridden”, it cannot be changed. At the bottom: Add a main hazard (a hazard from the answers shows 🔒, a hand-added one is removed with ×) and Add condition. If no active permit type covers a main hazard, the panel names it and approval stops.

  8. Approve it. Click “Approve — freezes the prescription”. The confirmation dialog (“This is what gets frozen”) spells out the consequence; Approve makes it final. If the button cannot be pressed, the reason is written below it (for example “There are still unanswered required questions.”).

Hazard identification and the live prescription

Section titled “Hazard identification and the live prescription”
The Hazard identification card: the tick-box lists A) Site-side hazards and B) Activity hazards, the Activity — additional questions and Material properties sections, and at the bottom Workplace and circumstances with the Explosive atmosphere zone picker and questions with a Yes/No/N/A switch.
The sections of hazard identification. The star (*) marks a mandatory question — here the explosive atmosphere zone.
The prescription of an approved assessment: at the top the permit to issue (one permit, supplements: hot work, Ex zone, lifting), below it the note on the mode, then the permit card with the supplements, the prescribed (locked) and recommended items and the minimum headcount.
The top of the prescription: with the built-in setting ONE permit to issue, the other hazards go onto it as supplements; below it the prescribed (locked) and the recommended items.

The page says: “Approved — the prescription is frozen: … prescribed permit(s).” The badge in the header reads Approved, and a card states: “Approved — the prescription is frozen.” The Verify button shows: “The content fingerprint MATCHES — the assessment has not changed since approval.”, together with when it was checked. The next step is creating the permit drafts: A permit from a risk assessment.

The Risk assessments list: the New risk assessment button at the top, the All / Draft / Approved / Superseded / Voided tabs below it, the Kind (All · Ad-hoc · Pre-prepared) and Scope (All · Plant · Whole site · Whole company) filters; in the rows the number, job (for a pre-prepared one also the kind and the version), a status badge (Approved, Superseded), site / plant, assessor, time of approval, the Validity (Valid until 2027-10-13, Expired: 2026-10-10, on an ad-hoc row: one job) and the chips of the prescribed permits.
The Prescribed permits column shows what the assessment prescribed; the chip of a permit that already exists is a link, and for a pre-prepared one the number of permits started from it stands above. A draft’s row says “after approval” — there is no frozen prescription yet.

When your organisation has pre-prepared assessments, the list can also be narrowed with the Kind and Scope filter buttons and a Superseded tab. For a pre-prepared assessment the Validity column shows the expiry (Valid until … · No expiry · expiring soon); on an ad-hoc row it says the assessment covers one job.

For recurring jobs (for example replacing a pump bearing) you do not need a new assessment every time: you make the pre-prepared assessment once and have it approved, and then it can be linked to any number of permits from the New permit drop-down while it is valid (see Requesting a work permit). The questions, the live prescription and the approval are the same as for an ad-hoc assessment; the differences are the kind, the scope, the expiry, and that the job’s concrete data is not on the assessment.

Step 1 of the New risk assessment page at V3 blokk: Recurring job (pre-prepared) selected in the Kind picker, with its explanation below; the Site (V3 blokk) and Plant (— Whole site —) fields are optional, with the scope explanation under them; further down job title and place, the note that the time window, work order, contractor, supervisor and headcount are entered on the permit, the description and the Create — the questions open next button.
For the pre-prepared kind the Site and Plant are optional: what stays empty widens the scope (site, then company); what cannot be chosen is disabled, with a reason.
  1. Click “New risk assessment”, and in the Kind chooser pick “Recurring job (pre-prepared)”. Under it you read: “Covers a recurring type of work; once approved it can be chosen for any number of permits from the “New permit” drop-down while it is valid.” If the kind cannot be chosen, the ⓘ next to the chooser says why: “Recurring jobs can be switched on in the policy (Permit settings → Risk assessment and preparation).”

  2. Set the scope with the Site and Plant fields — for a recurring job both are optional. Both filled in: the assessment can be chosen only for permits of that plant. Site only: for permits of any plant on that site (the plant comes from the permit) — the Plant field on All plants on the site, the default. Site empty too (— Whole company —): for any permit on every site (the site and plant come from the permit). What cannot be chosen is disabled, with a reason — for example “Whole company: only someone with access to every site can make a company-wide assessment.”; a site where the policy does not allow it reads “not allowed here”.

  3. Give the type of work a title and, if needed, a description. The form does not ask for the job’s concrete data: “The time window, work order, contractor, supervisor and headcount are entered on the permit — a pre-prepared assessment covers a type of work, not one specific job.” The assessment gets a KE- number; a company-wide one looks like KE-2026-CÉG-00001 (“CÉG” marks the company-wide series).

  4. Fill in the questions and approve it. Exactly like an ad-hoc assessment. The approval window also states the validity: “On approval the validity is fixed: 12 months (per the policy).” (or “… no expiry …”).

  5. After approval the “Create permit drafts” button does not appear; the Permits from this card does. For each prescribed permit type there is a New permit from this: … button (the type’s name follows) that opens the New permit page with the assessment and the type filled in; you enter the job’s data — time window, work order, contractor — there. Any number of permits can start from the same assessment.

While the assessment is still a draft, the Change kind and scope button lets you switch to another kind or scope. Switching from ad-hoc to pre-prepared clears the job-specific data (contractor, supervisor, work order, time window, headcount) — these go on the permit. Moving to another site or to company level gives the draft a new number in the new series.

Making, approving, versioning and withdrawing a pre-prepared assessment all need ptw:assess. A company-wide assessment can only be made, approved and withdrawn by someone with access to every site; a site-level one (without a plant) by someone with access to that site. The page does not hide a level that cannot be chosen; it shows it disabled, with a reason. Creating and approving an assessment follows the policy of the scope’s site (for a company-wide assessment, the company-level setting). When it is used, however, the policy of the permit’s site decides: the New permit drop-down and the expiry both read it — the same company-wide assessment can expire sooner on a site that sets a shorter validity.

The validity of a pre-prepared assessment is fixed at approval, but your organisation’s current policy counts too. The effective expiry is the earlier of the two: the expiry fixed at approval, and the day of approval plus the number of months now set in the policy row “Validity of a prepared risk assessment (months)”.

  • Tightening takes effect immediately, on assessments that are already approved too: if you shorten it in the policy, assessments fixed as valid for longer expire by the shorter rule.
  • Loosening does not extend them: if you later set a longer time, the already approved ones live until the expiry fixed for them.
  • An assessment is valid until the end of the expiry day — in the assessment’s time zone, and for a company-wide one in the organisation’s time zone.
  • It can have no expiry (0 months in the policy). An ad-hoc assessment never expires.

What happens when a pre-prepared assessment has expired or has been withdrawn:

Situation What happens
Starting a new permit It does not appear in the New permit drop-down, and no new permit can be linked to it.
A draft linked to it, not yet issued It cannot be issued. A reason stated in words stops the issue (“The prepared risk assessment linked to this permit has expired. Create a new draft with a valid assessment.”, or “… was withdrawn …”). This is a fixed core guard, it cannot be switched off. On the draft’s page the New draft with a valid assessment button walks you through starting over.
Expiry coming up The page signals an expiry within 30 days: expiring soon in the drop-down and the list, and on the draft’s bar on the permit page. The system sends no other reminder.
A permit already issued and running It does not stop. Extension, the daily restart and the handover do not check the assessment. The permit’s card says: “The permit runs on the version bound at issue.”
A standing permit If the assessment expires before the permit ends, the page gives a note (“The permit keeps running … start the next permit with a valid assessment.”) — it is not a block.
A closed permit Nothing; the record PDF keeps the state at closing.

The content of an approved assessment cannot be changed — the database protects it too. If the assessment of the type of work changes, open the assessment (or the list’s ⋮ menu) and click Review (new version). A copy is made as a draft, with a new number and the same content. Look over the answers — the page says: “This is a new version of …. Review the answers; on approval the previous version can be superseded.” — edit them and approve.

On approval the predecessor is superseded by default: in the approval window the Supersede the previous version (…) tick is on, and it can be switched off (then both versions stay selectable in the drop-down).

  • The superseded version no longer appears in the drop-down.
  • Its linked drafts not yet issued stay issuable.
  • Permits already issued are unaffected: they always keep the (old) version bound to them. The Versions list on the assessment page shows the other members of the chain.
The bottom of an approved pre-prepared assessment page: the Permits from this (1) card with the New permit from this: Hot work permit button and the draft PTW-2026-V3BLOKK-00024 started from it; the New version and withdrawal card with the Review (new version) and Withdraw buttons, each with its consequence below; at the bottom the Versions list: version 1 KE-2026-V3BLOKK-00001 Superseded, version 2 KE-2026-V3BLOKK-00004 (this one) Approved.
The page of version 2: a permit can be started from it, Review makes a further version, and after withdrawal no new permit can be linked to it.

You can withdraw a pre-prepared assessment from the approved state too: on the New version and withdrawal card of the assessment page, or in the list’s ⋮ menu, with a reason (at least 5 characters). Withdrawing is not deleting: the assessment stays in the record, no new permit can be linked to it, its linked open drafts (the confirmation window says how many) become non-issuable, and permits already issued carry on, with the version bound to them. In the list a withdrawn pre-prepared assessment gets the Withdrawn badge.

You do not have to enter many assessments one by one: the Bulk import button on the Risk assessments list loads them from a spreadsheet, as drafts. You need the ptw:assess right.

  1. Download the template (Download the template (xlsx)). It is built from your organisation’s current question set: row 1 holds the column keys, row 2 the explanation (it is not data), and sheet 2 the site, plant and permit-type keys — only for the sites you can access.
  2. Fill in one assessment per row. The title is required; kind is library (recurring) or adhoc (one-off). On a recurring row site and plant are optional: with no site the row is company-level, with no plant it is site-level — exactly as on the New risk assessment form. Question columns look like q:section/item.
  3. Choose the file and click Check. By default only a check runs: the report lists problems row by row, in plain sentences (unknown key, missing title, a scope that is not allowed), and writes nothing. While there are errors, nothing is loaded. Warnings (for example Not yet approvable — missing: …) do not stop the load: what is missing can be completed in the app.
  4. Tick “Load as drafts” and submit again. Either every row is loaded or none is. The report lists the new KE- numbers.
  5. Approve the drafts on the list — one by one, or with Approve selected (see below).

If you made a mistake, the report’s Revert the batch button deletes the batch’s drafts that are not yet approved; approved ones stay. The same file cannot be loaded twice while the first load’s rows still exist. A company- or site-level row needs the same write scope as the form: if you cannot access every site, a company-level row gets the error You have no write access to this scope.

If your organisation starts with many pre-prepared assessments — for example, your existing paper assessments — they arrive as drafts: either you load them from a spreadsheet (see above), or OPEREX operations does. An approved assessment cannot be loaded: approval — the content fingerprint, the competence check, the expiry and the approver’s name — always happens here, by your hand. A loaded draft is marked Bulk loaded in the list and on the assessment page, with the date of the load; if you loaded it, you are its author, while an operations load has no author.

  1. In the Risk assessments list, switch to the Draft tab, and narrow by kind or scope if needed.
  2. Select the drafts: with the checkbox on each row, with the header checkbox (Select all visible drafts), or with Select drafts for approval in the list’s ⋮ List actions menu.
  3. In the bar above the list, click Approve selected. The window tells you how many assessments will be approved; if you have no valid OHS qualification on record and the policy warns in that case, you give the justification here — it is recorded on every row.
  4. After approval, Bulk approval result above the list says row by row what happened: Approved, or Cannot be approved: with the reason (for example an unanswered required question, or it was changed elsewhere meanwhile).

Each assessment goes through approval on its own, exactly as if you approved them one by one: its own completeness, prescription and competence checks, its own fingerprint and its own audit entry. Any that cannot be approved stays a draft and does not stop the others — open it, complete it and approve it on its own. At most 100 assessments can be approved at once; company-wide ones, here too, only by someone with access to every site. Selecting and approving need the ptw:assess right; without it the menu item is shown disabled, with the reason.

What you see Why What to do
“There are still unanswered required questions.” under the approve button A starred question was left unanswered. Open the bar’s list of missing items and click the item.
“No permit follows from the answers yet. Answer the questionnaire, or add a main hazard by hand.” No main hazard, and no active base permit. Look over the answers, or add a main hazard in Add a main hazard; the base permit is set in the risk assessment template.
“No active permit type can issue: …” No active permit type covers the job’s main hazard (e.g. hot work). Enable the matching permit template, or set its main hazard in the template editor.
“The job safety analysis needs at least one filled row (activity + control).” Your organisation made the step table mandatory. Add at least one row with an activity and a control measure.
“Your organisation’s policy allows only a qualified occupational-safety professional to approve an assessment, and yours is not on record.” The approver competence gate is on the block level, and your person record has no valid qualification (or no person record is linked to your user). Ask your administrator for the link and the document in the Person register.
“Approval did not start: saving the draft failed.” The page is saved before approval; this time that failed. Check your connection and try again.
“The assessment was changed elsewhere since this page was loaded, so it was NOT approved …” It was changed in another tab or by another user. Reload, look it over and approve again.
On a prescribed permit’s card: “There is no active template for this at your organisation — no draft can be created from it.” Your organisation has no (active) work permit template for this type. Your administrator can install or activate it on the Permit settings → Work permit templates tab.
“Recurring jobs can be switched on in the policy (…).” in the ⓘ next to the Kind chooser The policy does not allow a pre-prepared assessment on this site (or at company level). Ask the policy manager for one of the two drop-down options: Policy gates.
“A pre-prepared assessment cannot hold job-specific data (…) — these go on the permit.” You tried to enter a work order, time window, contractor, supervisor or headcount on the assessment. Leave them empty: you fill them in on the permit.
The Whole company scope is disabled, with a reason You do not have access to every site. Only someone with access to every site can make, approve and withdraw a company-wide assessment; choose the plant or site level, or ask them.
“This prepared risk assessment has expired — pick a valid one or create a new one.” on the New permit page The assessment has expired (or was withdrawn). Make a new version (Review) and approve it; or pick another, valid assessment.
  • An approved assessment cannot be changed. If the job changes, start a new one with Copy as draft (for a pre-prepared one this is Review (new version)), correct it and approve it — the permits already issued keep the old assessment, because that was the basis of the decision. At the top of the copy the page warns you: “This is a copy. Check it against the site: the earlier answers may not hold for this job.”
  • Voiding is not deleting. Void (from the list’s ⋮ menu, and on a draft also at the bottom of the editor) needs a reason (at least 5 characters); the assessment stays in the record, only no further permit starts from it. An ad-hoc assessment from which a permit has already started cannot be voided; a pre-prepared one is taken out of use with Withdraw (see above).
  • The system never fills in a declaration for you. The assessment can make a declaration mandatory on the permit, but the answer is given by a person.
  • The assessment also satisfies the “Hazard identification before issuing” gate: on a permit started from an assessment — ad-hoc or pre-prepared alike — the assessment’s card stands in place of Hazard identification.
  • The assessment has its own PDF (the PDF button in the header): on a draft it says of itself that it is a draft; an approved one carries a QR code. Details: Printing and PDF.
  • At approval the content is fingerprinted (answers, prescription, the job safety analysis steps), and on the assessment page the check tells whether it has changed since. How it works: Digital fingerprints — technical brief.
  • The assessment on the permit’s route: who does what from the risk assessment to closure, on one swimlane diagram — Permit to work — the process.